Finished a 3000A switchgear replacement in a live hospital — 14 hour window, zero unplanned outage Job Photos
Wrapped this two weekends ago and I am still coming down off it. 1978 switchgear feeding half a hospital campus, bus insulation failing, no replacement parts in existence.
The plan:
Weeks 1-6 — build the temp feed. 2000A of cam-lock from a rental 2MW genset into a temporary distribution section, tested and load-banked twice before we touched anything live.
Window — Saturday 18:00 to Sunday 08:00. Transfer to temp, demo, set new gear, terminate, test, transfer back.
Actual — transfer at 18:40, gear out by 22:15, new gear set and anchored by 01:30, terminations done at 05:10, megger and phase rotation by 06:20, retransfer at 07:05. Fifty-five minutes to spare.
The thing that made it work was not the schedule, it was that we ran the whole retransfer as a written sequence with one person reading and one person executing, out loud, like a checklist. Nobody touched anything that was not read aloud first. Sounds slow. Was not.
Six months of planning for fourteen hours of work. Worth every meeting.