First 400A underground service lateral — how'd I do?
Journeyman finally let me run point on a 400A underground service install this week. 240V single phase, 350kcmil aluminum in 3" rigid PVC, 65-foot run from the pad transformer to the meter base.
Used a Greenlee cable tugger for the pull — 350kcmil is no joke. Three conductors plus a 4/0 ground. The trench is 24" below grade per NEC 300.5.
Inspection is Thursday. Nervous but I think I got it right. Open to critique.